What ASTM E84 measures

ASTM E84 — the Steiner tunnel test — is the standard surface-burning test US building codes use for interior finishes. A 24-foot sample is mounted in a test tunnel, a controlled flame is applied, and two things are measured over ten minutes: how far flame spreads across the surface (the Flame Spread Index, FSI) and how much smoke the material develops (the Smoke Developed Index, SDI). Lower is better on both.

How the IBC classifies the results

The International Building Code sorts interior wall and ceiling finishes into three classes by their E84 indices:

IBC classFlame Spread IndexSmoke Developed Index
Class A0 – 25450 or less
Class B26 – 75450 or less
Class C76 – 200450 or less

Which class a given room requires depends on the occupancy type, the room's function, and whether the building is sprinklered — that call belongs to the project's design professional and the local building authority.

CeilEx membrane results, per finish

Each white CeilEx membrane finish was tested to ASTM E84 at Intertek. The results are reported per finish — because finishes burn differently, and a single blanket number for a whole catalog tells a code official nothing:

FinishFlame Spread IndexSmoke Developed Index
Gloss (lacquer)5300
Matte10300
Satin15250

Thickness, roll width and light transmission for every membrane, with each data sheet as an open PDF, are on the membrane data page.

The full reports, with laboratory identification and test conditions, are in Fire Performance Data FPD-100. The reports state the indices; the comparison against your project's code requirement is made by the design professional and the local authority.

Why per-finish reporting matters: when a plan reviewer asks "show me the test for this material," a per-finish report with the lab named answers the question in one attachment. A generic claim does not.

How to document it in a submittal

For a commercial project, pair the fire data with the rest of the package: the CSI Section 09 54 00 / 09 54 43 specification, the membrane data sheet for your selected finish, and light transmission data if the ceiling is backlit. The full path is in our specifier's guide.

Need fire documentation for a specific project?

We assemble the per-finish reports into your submittal package and can walk your plan reviewer through the data.

Become a Dealer Call